BRIDGE REPLACEMENT, ELM ST./CENTER ST. OVER THE TAUNTON RIVER

Project Overview

Project consisted of erecting 650-foot long temporary Acrow bridge over the Tauton River. The Acrow bridge was supported on H-pile foundation piles and precast pile caps. Cast-in-place concrete abutments and precast block wingwalls were constructed on the approaches. The project also consisted of the demolition of the existing steel truss bridge.

Project Overview

ChatGPT Image Jun 12, 2026, 06_34_07 PM.png

Client:
MassDOT

9f2f09b4-d13b-47ff-bc00-5011dd2430ba.png

Location:
BERKELEY/DIGHTON, MA