ROUTE 24 AND I-295 BRIDGE PRESERVATION

Project Overview

This RIDOT project involved the various repairs to eight highway bridges. The work in included steel beam strengthening repairs, 287 CF of concrete masonry repairs, 250 SF of bridge repairs with patching mortar, 13 EA bridge jacking and shoring for bearing replacement, and bridge deck/joint replacement. The work also included bridge preservation tasks such as bridge washing, application of concrete protective coatings, and bridge painting. The project required significant maintenance and movement of traffic (including setting of 2000 LF of temporary median barrier) on I-295 and Route 24.

Completed on time & on budget

Project Overview

ChatGPT Image Jun 12, 2026, 06_34_07 PM.png

Client:
RTDOT

9f2f09b4-d13b-47ff-bc00-5011dd2430ba.png

Location:
RTE 24 & I-95

bottom of page